Wednesday, 6 January 2016

ME2027 Process planning and cost estimation university questions


University question of unit wise 2 marks and 16 marks questions were repeatedly asking by the Anna University, Chennai for the subject process planning and cost estimation. This is one of the elective subjects for the students of Mechanical engineering studying VII semester. Take for your reference and get more marks in university examinations.

B.E/B.Tech Degree Examinations April/May 2013

Anna University, Chennai

Department of Mechanical Engineering

ME2027    Process Planning and Cost Estimation
Seventh Semester
Regulation 2008/2010

PART-A   (10*2=20 marks)

1. What is SIMO chart?
2. Define rating.
3. List the information requires for process planning.
4. What are the two approaches to process planning?
5. Define costing.
6. What is meant by direct material? Give an example.
7. Mention any two functions of cost estimation.
8. What do you meant by a realistic estimate?
9. What is meant by direct labor cost?
10. What is fatigue allowance?

PART-B   (5*16=80 marks)

11.(a)         (i) What are the steps followed for doing a method study of job process? (8)
                   (ii) Write procedure of time study. (8)
Or

  (b)            (i) What is the purpose of work measurement? Enumerate its uses. (8)
                   (ii) Discuss the tools are techniques for work measurement. (8)

12. (a)        Explain the technological frame work of process planning by using a block diagram. (16)
Or
     (b)         (i) Write the process planning procedure. (8)
                   (ii) What are the factors to be considered in machine selection? (8)

13. (a)        (i) Discuss the various methods of costing. (16)

Or

      (b)        (i) Name the various elements of cost. Explain each element in detail. (16)
14. (a)        (i) What are the components of a job estimate? Explain. (16)

Or

     (b)         (i) What are the types of estimator.  (8)
                   (ii) Differentiate between estimating and costing. (8)

15. (a)        Explain the various time allowances which should be considered for calculating labor cost. (16)

Or

     (b)         Explain the procedure followed for estimating the cost of an industrial product. (16)

B.E/B.Tech Degree Examinations April/May 2015

Anna University, Chennai

Department of Mechanical Engineering

ME2027    Process Planning and Cost Estimation
Seventh Semester
Regulation 2008/2010

PART-A   (10*2=20 marks)

1. What is meant by method study?
2. Define standard time.
3. What are the types of process planning?
4. List the information required for process planning?
5. Define cost accounting.
6. Write any two objectives of cost estimation.
7. What is batch costing?
8. Define standard data.
9. What is meant by overhead expenses?
10. Define cutting speed.

PART-B   (5*16=80 marks)

11.   (a) With examples explain the objectives of work study. (16)

Or

          (b) Discuss the various tools and techniques used for work        measurement. (16)

12.    (a) Explain the process planning procedure. (16)

Or
(b) Describe the various types of charts and diagrams used in process planning. (16)

13.    (a) Name the various elements of cost. Explain each element in detail giving suitable examples. (16)

Or

          (b) Write down the step by step procedure for estimating the direct material cost.  (16)

14.    (a) What are the types of estimates? Explain with examples. (16)
Or
          (b) Explain various allowances to be considered in estimation of direct labor cost. (16)

15.    (a) A 60 mm rod of aluminum to be machined on a lathe, the finished size is shown in fig. The length of rod is 175 mm. Determine the total machining time and material cost, if material is purchased at the rate of Rs 12 per Kg. Assuming cutting speed 30 m/min and feed 0.2 mm/rev. Take density of aluminum as 2.7 gm/cc. Depth of cut not to exceed 2.5 mm.  (16)


Or

          (b) Describe the procedure of estimating the machining time required during shaping operation of a shaper. (16)

No comments:

Post a Comment